FPLT-AFDAT = FPLT-FKDAT (BILLING_SCHEDULE_GENERATE) CJV4

$
0
0

Hi,

 

What has to happen:

Copy a project with its source version into a target version setting up a perfect copy.

 

What do i use:

CJV4

 

What is happening?

When performing a copy of a project's photo into another photo it copies well the Billing Plan but the schedule is changed (Dates).

When i went closer into investigating i found out that FPLT-FKDAT is set into FPLT-AFDAT (changing the AFDAT).

 

Steps when performing: CJV4

==> OBJECTS_MAINTAIN (LOOP AT WORK)
==> NETWORK_ACTIVITY_MAINTAIN

==> NETWORK_ACTIVITY_CREATE_W_REF

==> CO20_ACTIVITY_CREATE_WITH_REF

==> CN_PP_FPLA_COPY

==> CN_PP_BILLING_SCHEDULE_COPY ==> COPY_FPLT

==> BILLING_SCHEDULE_GENERATE ==> TERMINE_ERZEUGEN ==> REFERENZPLAN_FUELLEN.

 

Within REFERENZPLAN_FUELLEN you can see that DA_FPLT is being looped at and is set to FPLT.
Then at the end of the loop you can find the folowing statement FPLT-AFDAT (Billing date) = FPLT-FKDAT (Settlement date).

AFDAT_FKDAT.PNG

Questions

Why is the Billing date been set to the Settlement date here? As this will not be a perfect copy from the previous photo.

How can i get the correct settlement date from previous project version?

 

By manually copying the FPLT table values into the new VALUES after performing CJV4? or is there any other way?